OAK MOUND – WALDO RUN

TRANSMISSION PROJECT

PROJECT NAME

Oak Mound – Waldo Run

The Oak Mound – Waldo Run project included the construction of approximately 18 miles of new, double-circuit 138kV transmission line from the expanded Oak Mound substation to the new Waldo Run substation near Bridgeport, WV. The line was designed using two-pole tubular steel structures with poured foundations for all dead-end and heavy-angle structures. Direct embedded foundations with concrete backfill were used for all other structures. Dead-end and angle structures also required down guys with grouted rock anchors. Access roads and drilled shaft foundation construction were contracted separately.

CLIENT

FirstEnergy / Mon Power

PROJECT LOCATION

Bridgeport, West Virginia

COMPLETION DATE

August 2016

Notable Project Accomplishments

The transmission line was constructed through a very mountainous and challenging terrain, requiring special logistical planning in order to accommodate access of cranes, concrete trucks, and other construction equipment. Installation of guy anchors required installation of grout for anchorage into rock. The unique design required specialized equipment and installation techniques.  Additionally, due to the challenges of the mountainous terrain, helicopters were used for wire stringing operations.

Related projects

Darlington

Akron Children’s- Kay Jewelers Pavillion

Oceanview

JW Didado Corporate Logo - Primary Reversed

AKRON (Corporate Headquarters)
1033 Kelly Ave.
Akron, Ohio 44306
P: 330-374-0070

SYRACUSE
7822 Morgan Road
Liverpool, NY 13090
P: 315-409-4519

ABOUT J.W.DIDADO

LEADERSHIP

SAFETY

EQUIPMENT

HOW WE BUILD

SERVICES

RESIDENTIAL

COMMERCIAL & INDUSTRIAL

TRANSMISSION & DISTRIBUTION

SUBSTATION

TELECOM

EMERGENCY & STORM RESTORATION

NOTABLE PROJECTS

COMMUNITY OUTREACH

CAREERS

GO ON STORM WITH US

ASSET MANAGEMENT PROGRAM

FOLLOW US ON SOCIAL